SIAZAKH WATER PUMP STATIONS

Project Short Description

The scope of contract includes engineering, procurement, construction and commissioning of electrical and mechanical equipment of two  pump stations number 4 and 5 .The station number 4  consists of 8 (vertical split case ) high pressure pumps with flow of 1005 lit/s and head pressure of 104 m . The electro motors of pumps are 6.6 KV with capacity of 1450 kW . The station number 5 consists of 5  (horizontal split case ) high pressure pumps with flow of 1625lit/s and head pressure of 47 m . The electro motors of pumps are 6.6 KV with capacity of 1250 kW . The contract activities are mainly involved of piping , equipment of pumping , surge tanks , 12.5 , 5  tons overhead cranes in mechanical part and 400 V,6 KV ,20 KV transformers ,400 V,6.6 KV electrical distribution panels in electrical part and control , instrumentations and telemetry in control systems . All buildings and pump station yard mechanical and electrical construction activities are also included in the scope of contract.

  • FIELD : WATER PUMP STATIONS , WATER & WASTEWATER TREATMENT PLANTS
  • CONTRACT NUMBER : 25104/100/400
  • CONTRACT DATE : 94/9/8
  • CLIENT /CUSTOMER : KURDISTAN PROVINCE WATER AUTHORITY
  • CONSULTANT : ABBNIROO CONSULTING ENGINEERS
  • CONTRACTOR : TAVAAN AZMAYAN TECHNICAL & CONSTRUCTION COMPANY
  • CAPACITY :
  • PROJECT STATUS : UNDER CONSTRUCTION
  • PROJECT INITIAL DURATION : 12 MONTHS
  • START DATE : 94/10/8
  • END DATE : …
  • PROJECT SITE LOCATION : DIVANDAREH TOWN IN KURDISTAN PROVINCE
  • PROJECT SITES NUMBERS : 2 , PUMP STATIONS NO. 4,5
keyboard_arrow_up