NOOR ABAD WASTEWATER TREATMENT PLANT

Project Short Description

The Noor Abad wastewater treatment project in capacity of 24400 m3/h has been designed and constructed in 2km of Noor Abad town of Mamasani province and 180 km from Shiraz main city. The plant serves the population of 125000 person in active wastewater method of A2O type (MLE) and wide depth aeration. The scope of contract was design, procurement, installation and commissioning of civil construction, mechanical, electrical, control, instrumentation, and six months tentative operation of the plant.

  • FIELD : WATER PUMP STATIONS , WATER & WASTEWATER TREATMENT PLANTS
  • CONTRACT NUMBER : 440/5993
  • CONTRACT DATE : 1388/2/22
  • CLIENT /CUSTOMER : FARS WATER & SEWAGE WATER COMPANY
  • CONSULTANT : TOOS ABB CONSULTING ENGINEERS
  • CONTRACTOR : TAVAAN AZMAYAN TECHNICAL & CONSTRUCTION COMPANY
  • CAPACITY : 24400 M3/DAY
  • PROJECT STATUS : EXECUTED
  • PROJECT INITIAL DURATION : 24 MONTHS
  • START DATE : 1388/3/3
  • END DATE : 1392/12/18
  • PROJECT SITE LOCATION : NOOR ABAD TOWN , FARS PROVINCE
  • PROJECT SITES NUMBERS : 1 , SEWAGE WATER TREATMENT PLANT